PMAOPS521C - Plan plant shutdown
Description |
This competency covers the planning of work to be done in a plant shutdown or outage, eg maintenance or inspection shutdown of a plant. |
Pre Requisites |
Nil |
Application |
In a typical scenario, a senior plant technician takes a lead technical role in the planning of a plant shutdown such as the maintenance/pressure vessel inspection shut. This competency requires the application of a detailed plant knowledge to the task of developing a detailed shutdown plan. This competency is not actually about the shutting down of the plant itself (see PMAOPS411B Manage plant shutdown and restart), nor decommissioning (see PMASUP441C Decommission plant) but rather about the planning for the activities which will occur during a planned, major shutdown. Shutdown planning is usually a team activity and so this technician would also be working with technical (process) experts, maintenance experts, contractor representatives and liaising with production and other management. The reasons for the shutdown could include:
|
Performance Criteria |
1. Identify maintenance/project and plant requirements. 1.1. Analyse relevant company records to determine activities which have been scheduled for the shutdown 1.2. Obtain information on maintenance activities intended for the shutdown 1.3. Obtain information on production activities intended for the shutdown 1.4. Obtain information on projects or construction activities intended for the shutdown 1.5. Compile a list of all activities intended for the shutdown, including sufficient detail to allow for shutdown planning 1.6. Negotiate conflicts between proposed activities. 2. Identify tasks, timelines and resources. 2.1. Break down each agreed shutdown activity into required tasks 2.2. Determine time, people, material, other resources required and 'owner' for each task 2.3. Determine prerequisite tasks for each task 2.4. Identify conflicts between tasks arising from resources or other causes 2.5. Negotiate conflicts between tasks 2.6. Compile database of all tasks and their requirements. 3. Develop schedule. 3.1. Develop draft shutdown schedule (including planning activities) 3.2. Determine critical path for shutdown tasks 3.3. Analyse tasks on critical path to determine methods of reducing critical path 3.4. Develop revised schedule 3.5. Consult with all relevant stakeholders and analyse revised schedule for conflicts and possible savings 3.6. Negotiate conflicts 3.7. Develop final schedule and critical path. 4. Communicate with all relevant stakeholders. 4.1. Contribute to shutdown planning meetings with stakeholders. 4.2. Meet with stakeholders individually 4.3. Prepare reports and documents as required 4.4. Ensure all permissions required for tasks have been obtained 4.5. Liaise with suppliers and contractors to obtain parts, materials and services. 5. Monitor shutdown. 5.1. Establish systems to allow monitoring of shutdown to schedule 5.2. Monitor progress to schedule 5.3. Identify causes of not meeting schedule 5.4. Negotiate a solution to cause 5.5. Adjust schedule to meet changed circumstances but still meet overall timeline (if at all possible). |
Required Skills & Knowledge |
Required skills Competence includes the ability to:
Required knowledge Competence includes an understanding of the operation of the plant and its units including:
|
Range Statement |
Codes of practice/ standards Where reference is made to industry codes of practice, and/or Australian/international standards, the latest version must be used. Context This unit of competency includes all such items of equipment and unit operations which are covered by the shutdown. Where only a plant area is being shut (or one plant in an integrated complex), it also includes the impact of the shut on those areas still operating. Databases may be:
Scheduling may include:
Procedures Procedures may be written, verbal, computer-based or in some other form. They include:
Health, safety and environment (HSE) All operations to which this unit applies are subject to stringent health, safety and environment requirements, which may be imposed through State or Federal legislation, and these must not be compromised at any time. Where there is an apparent conflict between Performance Criteria and HSE requirements, the HSE requirements take precedence. |
Evidence Guide |
Context of and specific resources for assessment Assessment will require access to an operating plant over an extended period of time, or a suitable method of gathering evidence of operating ability over a range of situations. A bank of scenarios/case studies/what-ifs will be required as will a bank of questions which will be used to probe the reasoning behind the observable actions. Method of assessment In all plants it may be appropriate to assess this unit concurrently with relevant teamwork and communication units. It may be appropriate to co-assess this unit with
Guidance information for assessment Assessment processes and techniques must be culturally appropriate and appropriate to the oracy, language and literacy capacity of the assessee and the work being performed. |
- Courses
- Units of Competency
Traning
- Adult Education Principles
- Aviation Consultancy
- Competency Mapping
- Course Design
- Customised Training
- Emergency Evacuation Plans
- Escorted Entries
- Gap Analysis
- Job & Competency Profiling
- Mentoring
- Premium Support
- Procedures Development
- Risk Management
- Quality: Continuous Improvement
- Training & Assessment Systems: Evaluation and Analysis
- Training & Assessment System Development
- Training Needs Analysis
Services
Copyright © 2011Risk Response + RescueAll Rights Reserved Terms & Conditions Disclaimer Privacy PolicyImprint

